- First is based on door count. Average kitchen size is 20-25 doors with 5-8 drawer fronts
- Next is crown moulding and trim optional installation. 2-3 hrs
- Counter top installation option. 2-3 hrs
- Cabinet modifications. Each modification takes 1-2 hours. Example... cut down stove or fridge cabinet.
- Rollout installation or drawer replacement. 1/2-3/4 per drawer
- Is the customer removing the doors and drawer fronts. 1 hr
- Is the customer removing and disconnecting the sink and,countertop?, 1-1-1/2
These points are the major time consuming parts of the refacing job.
, ,So an average kitchen with the number of doors and drawers fronts listed will take one fully experienced kitchen person to reface a kitchen,3-4 days working ,8 hours a day to complete.
If the consumer can do some of the work. At least a half a day can be saved in time.,
Again every installer works at a different pace based on his or her experience.
,